Application Of The Line Of Balance Method In The Scheduling Of High-Rise Building Construction In Bandung City (Case Study: UNIPI Bandung Campus Building Construction Project)
DOI:
https://doi.org/10.55227/ijhet.v5i3.1123Abstract
The construction of high-rise buildings requires effective scheduling methods to ensure project completion according to time, cost, and quality targets. This study aims to analyze the effectiveness of the Line of Balance (LOB) method compared with the Bar Chart method in scheduling structural work on the UNIPI Bandung Campus Building Construction Project. This research used a quantitative comparative method based on secondary data, including project schedules, work durations, and repetitive structural activities such as columns, beams, slabs, and stairs. The analysis was conducted by developing LOB schedules using average and minimum lag times, followed by a comparison of project duration and time efficiency. The results showed that the LOB method using minimum lag time produced the shortest duration, reducing the project completion time from 24 weeks to 20 weeks with a time efficiency of 16.67%. The total project cost remained unchanged, but the weekly cost distribution differed due to accelerated work progress. The LOB method is effective for optimizing repetitive construction scheduling and improving workflow continuity.
Downloads
References
Andika, I., Lim, S., Nevile, S., Satya, R., & Farisi, A. (2024). Analisis sistem informasi manajemen proyek: systematic literature review. JATISI, 11(1).
Anggraini, S., & Sormin, C. (2025). Implementation of the Critical Path Method in Optimizing the Orthodox Black Tea Processing. ZERO: Jurnal Sains, Matematika dan Terapan, 8(2), 80-89.
Arianto, A. (2010). Eksplorasi Metode Bar Chart, CPM, PDM, PERT, Line of Balance Dan Time Chainage Diagram Dalam Penjadwalan Proyek Konstruksi. Universitas Diponegoro, http://eprints.undip.ac.id/38831/1/Tesis.pdf
Aulia, M. A., Farisi, A. H., Wibowo, M. A., & Hidayat, A. (2017). Analisis Penggunaan Metode Penjadwalan Line of Balance Pada Proyek Konstruksi Repetitif (Studi Kasus: Proyek Pembangunan Apartemen Candiland–Semarang). Jurnal karya Teknik sipil, 6(1), 127-137.
Ervianto, Wulfram, I. (2005), Manajemen Proyek Konstruksi (Edisi Revisi), Edisi III, Andi, Yogyakarta.
Ferdyawan, F., & Hajjah, A. (2020). Penerapan Algoritma Genetika Dalam Optimasi Penjadwalan Proyek. Jurnal Mahasiswa Aplikasi Teknologi Komputer dan Informasi
Geraldi, J., & Lechter, T. (2012). Barcharts revisited: A critical analysis of its roots and implications to the management of projects today. International Journal of Managing Projects in Business, 5(4), 578-594.
Gerwin, D., & Lewis, J. D. (1990). Line of Balance scheduling. Journal of Construction Engineering and Management, 116(2), 265–286. https://doi.org/10.1061/(ASCE)0733-9364(1990)116:2(265)
Gould, F. E., & Joyce, N. E. (2014). Construction project management (4th ed.). arson Education.
Gunanto, R., Lapian, F. E., Mabui, D. S., Mayaindrawati, C., & Riswanto, S. (2024). ANALISIS PENGGUNAAN METODE LINE OF. BALANCE (LOB) PENJADWALAN. PROYEK KONSTRUKSI BERULANG (PERUMAHAN KHUSUS MASYARAKAT 15 UNIT KABUPATEN KEROM). Cyclops: Jurnal Teknik Sipil dan Perencanaan, 2(2), 64-70.
Hafnidar, A. R. (n.d.). Manajemen proyek konstruksi. Retrieved from https://ftp.idu.ac.id/wpcontent/uploads/ebook/ip/BUKU%20MANAJEMEN%20PROYEK/Manajemen_Proyek_Konstruksi_Hafnidar_pdf.pdf
Harmelink, D. J., & Rowings, J. E. (1998). Linear scheduling model: Development of controlling activity relationships. Journal of Construction Engineering and Management, 124(4), 263–268. https://doi.org/10.1061/(ASCE)0733-9364(1998)124:4(263)
Hegazy, T. Wassef. N. 2001. Cost Optimization in Projects with Repetitive.
Hendrickson, C. (2008). Project management for construction: Fundamental concepts for owners, engineers, architects and builders (Version 2.2). Carnegie Mellon University. Retrieved from http://pmbook.ce.cmu.edu/
Hinze. 2008. Construction Planning Scheduling Pearson.
Husen, Abrar, (2008), Manajemen Proyek, Penerbit Andi, Yogyakarta.
Kalia, S. M., Utiarahman, A., & Tuloli, M. Y. (2022). Penerapan Metode Line of Balance Pada Proyek Konstruksi Repetitif (Studi Kasus: Perumahan Griya Tunas Mandiri). Jurnal Penelitian Jalan Dan Jembatan, 2(2).
Kenley, R., & Seppänen, O. (2010). Location-based management for construction: Planning, scheduling and control. Spon Press.
Kerzner, H. (2017). Project management: A systems approach to planning, scheduling, and controlling (12th ed.). John Wiley & Sons.
Lestari, D. (2018). Penerapan Metode Line of Balance pada Pembangunan Perumahan (Studi Kasus pada Perumahan Permata Puri Ngaliyan Semarang). Jurnal Teknik Sipil, 9.
Liauw, J. J., Lusiana, L., & Syahrudin, S. ANALISIS PENJADWALAN DENGAN MENGGUNAKAN METODE LINE OF BALANCE PADA PROYEK KONSTRUKSI REPETITIF (STUDI KASUS PROYEK PEMBANGUNAN PERUMAHAN KOMPLEK TNI JALAN ARTERI SUPADIO). JeLAST: Jurnal Teknik Kelautan, PWK, Sipil, dan Tambang, 9(4).
Lucko, G., & Gattei, G. (2016). Line-of-balance against linear scheduling: Critical comparison. Proceedings of the Institution of Civil Engineers-Management, Procurement and Law, 169(1), 26-44.
Meredith, J. R., & Mantel, S. J. (2012). Project management: A managerial approach (8th ed.). John Wiley & Sons.
Mohan, S., & Gopalakrishnan, K. (2019). Scheduling of repetitive construction projects using geographic information systems: An integration of critical path method and Line of Balance. Journal of Infrastructure Systems, 25(2), 04019012. https://doi.org/10.1061/(ASCE)IS.1943-555X.0000515
Patiroi, A. N. F., Bachmid, S., & Muin, S. A. (2022). Tinjauan Penjadwalan Proyek dengan Menggunakan Metode Line of Balance pada Proyek Pembangunan Instalasi Perpipaan Air Limbah Paket C-3 Kota Makassar. Jurnal Ilmiah Mahasiswa Teknik Sipil, 4(2), 260-266.
Prasetyo. 2017. Analisis Penjadwalan Ulang Waktu Pelaksanaan Proyek Jalan dengan Line of Balance, Tessis, Universitas Islam Indonesia, Yogyakarta.
Project Management Institute. (2013). A guide to the project management body of knowledge (PMBOK guide) (5th ed.). Project Management Institute, Inc.
Putra, A. P. A., & Sarya, G. (2022). Analisis Penjadwalan dan Alokasi Biaya Menggunakan Metode Line of Balance Pada Proyek Jalan dan Jembatan Frontage Road Waru-Buduran. Jurnal Kacapuri: Jurnal Keilmuan Teknik Sipil, 5(1), 390-397.
Rachman, S. (2018). Line of Balance pada proyek pekerjaan struktur gedung bertingkat. Jurnal Rekayasa Sipil, 12(1), 45–58.
Raidyarto, A., & Widiati, I. R. (2023, May). TINJAUAN PENJADWALAN PADA PROYEK PEMBANGUNAN GEDUNG MAJELIS RAKYAT PAPUA (MRP) DENGAN METODE LINE OF BALANCE (LOB). In Prosiding: Seminar Nasional Teknik Sipil Universitas Yapis Papua (Vol. 2, No. 1, pp. 058-065).
Rani, H. A. (2016). Manajemen Proyek Konstruksi.
Renwarin, P., Jamlaay, O., & Hutubessy, V. R. R. (2025). Analisa Penjadwalan Dengan Metode CPM dan Line of Balance pada Pembangunan Proyek Perumahan Citraland Ambon. Jurnal Multidisiplin Ilmu Akademik, 2(1), 696-709.
Rowings, J. E., & Harmelink, D. J. (2004). Linear scheduling using automated tools and techniques. Journal of Construction Engineering and Management, 130(2), 202–213. https://doi.org/10.1061/(ASCE)0733-9364(2004)130:2(202)
Sacks, R., & Goldin, M. (2007). Lean management model for construction of high-rise apartment buildings. Journal of Construction Engineering and Management, 133(5), 374–384. https://doi.org/10.1061/(ASCE)0733-9364(2007)133:5(374)
Saputra, I. H., Erina, Y., & Rodhi, N. N. (2024). Analisis Pengendalian Waktu dan Biaya Proyek Konstruksi Dengan Metode CPM (Critical Path Method). Innovative: Journal Of Social Science Research, 4(6), 7797-7807.
Sears, S. K., Sears, G. A., & Clough, R. H. (2015). Construction project management: A practical guide to field construction management (6th ed.). John Wiley & Sons.
Simamora, Y., & Nuswantoro, W. (2008). Studi Penjadwalan Waktu dengan Metode Line of Balance (LOB) untuk Membangun Perumahan Pasca Bencana Tsunami Di NAD (Studi Kasus Pembangunan Perumahan Di Calang). Jurnal Rekayasa Rancang Bangun, 9(1), 1-9.
Siswanto. (2010). Operasi riset (2nd ed.). Erlangga.
Soeharto, I. (1999). Manajemen proyek: Dari konseptual hingga operasional (2nd ed.). Erlangga.
Sudarso, T., & Yohanes, J. J. (2012). Analisis penjadwalan pekerjaan berulang pada proyek gedung bertingkat menggunakan Line of Balance. Jurnal Infrastruktur Sipil, 8(2), 125–140.
Timothy, A., & Gondokusumo, O. (2022). PENJADWALAN PROYEK PERUMAHAN X BINTARO DENGAN METODE LINE OF BALANCE YANG DISEMPURNAKAN. Jurnal Muara Sains, Teknologi, Kedokteran dan Ilmu Kesehatan, 6(2), 281-290.
Tistogondo, J., Septianto, D. A., & Wulandari, D. A. R. (2025). Analisa Pengendalian Waktu Proyek Dengan Menggunakan Metode LOB (Line of Balance) Pada Proyek Perumahan Citragarden Sidoarjo. Ge-STRAM: Jurnal Perencanaan Dan Rekayasa Sipil, 8(1), 1-6.
Tjandra, M. S., & Gondokusumo, O. (2022). Penjadwalan Proyek Perumahan X Di Tangerang Selatan Dengan Metode Line of Balance Dan Efek Pembelajaran. JMTS: Jurnal Mitra Teknik Sipil, 169-184.
Uher, T. E. (n.d.). Essentials of construction project management. Retrieved from https://archive.org/details/essentialsofcons0000uher
Ullah, N., Rakesh, R., Shariar, F., Ahmed, S., Sakib, K., & Chowdhury, T. (2023). Effects of Triple Constraints on Project Success: Evidence from Bangladesh.
Widina Media Utama. (n.d.). Manajemen konstruksi. Retrieved from https://repository.penerbitwidina.com/media/publications/618693-manajemen-konstruksi-4450dbb5.pdf
Widodo, S. (2022). Analisis Penjadwalan Proyek Dengan Metode Line of Balance Pada Proyek Pembangunan Perumahan Grand Efata Malibela. Jurnal Teknik Sipil: Rancang Bangun, 8(1), 115-123.
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2026 Fajar Rizka Juniar, Odih Supratman, Siti Nurasiyah

This work is licensed under a Creative Commons Attribution-NonCommercial 4.0 International License.