Value Engineering, Diaphragm Wall, Strutting & King Post, Balanced Budget, Value Index

Abstract

This study evaluates the change in a deep-excavation retaining system from Strutting & King Post to Diaphragm Wall at the Harapan Kita–Tokushukai Heart Hospital Project using a Value Engineering approach with a balanced-budget criterion. A quantitative comparative-evaluative case-study design was applied. Primary data were obtained from 12 project professionals purposively selected from an operational population of 19 personnel, while secondary data included cost estimates, bills of quantities, design and geotechnical documents, schedules, Value Engineering documents, and change-order records. The analysis combined FAST, Cost/Worth Ratio, instrument validity and reliability, descriptive statistics, Shapiro-Wilk testing, Wilcoxon Signed-Rank testing, weighted performance, cost reconciliation, balanced-budget analysis, and Value Index calculation. The Diaphragm Wall alternative achieved higher technical performance and constructability, shortened the affected works by approximately eight weeks, and reduced cost from IDR 25.445 billion to IDR 25.031 billion, equivalent to 1.63% savings. Weighted performance increased from 3.0532 to 3.9826, while the Value Index rose from 0.611 to 0.810. The alternative therefore provided higher value for this case, subject to technical, contractual, and safety verification before implementation.

Downloads

Download data is not yet available.

References

Amran, M.A., Wibowo, P.D. & Adriansyah. (2019). Faktor yang berpengaruh dalam penerapan value engineering pada pekerjaan D-Wall di bangunan gedung menggunakan metoda RII. Rekayasa Sipil 8(1): 10-17. https://doi.org/10.22441/jrs.2019.v08.i1.02

Anthony, A., Wahyuningtyas, I.S. & Farkhantiansyah, A. (2024). Case study of double-wall retaining wall system for deep excavation in Jakarta, Indonesia. Indonesian Geotechnical Journal 3(3): 1-16. https://doi.org/10.56144/igj.v3i3.103

Asa, M.F., Iskandar, S., Karim, S.B.B.A. & Berawi, M.A. (2025). Cost-Saving Strategy Using Value Engineering Analysis on Basement Construction Work. International Journal of Technology 16(6): 2194-2210.

Badan Standardisasi Nasional. (2017). Persyaratan Perancangan Geoteknik (SNI 8460:2017). Jakarta: Badan Standardisasi Nasional.

Chiu, H.-W., Hsu, C.-F., Tsai, F.-H. & Chen, S.-L. (2024). Influence of Different Construction Methods on Lateral Displacement of Diaphragm Walls in Large-Scale Unsupported Deep Excavation. Buildings 14(1): 1-29. https://doi.org/10.3390/buildings14010023

Husin, A.E. (2019). Performance improvement of diaphragm wall at high rise building by value engineering utilization. ARPN Journal of Engineering and Applied Sciences 14(18): 3301-3309.

Nong, X., Wang, Y., Lin, B., Luo, W. & Tang, R. (2024). Performance of Diaphragm Walls during Ultra-Deep Excavations in Karst Areas: Field Monitoring Analysis. Advances in Civil Engineering 2024: 1-15. https://doi.org/10.1155/2024/5834253

Pitaloka, A.D., Khamim, M. & Lydianingtias, D. (2021). Analisa perbandingan pelaksanaan secant pile dengan diaphragm wall sebagai perbaikan pondasi Bendungan Semantok. Jurnal Online Skripsi Manajemen Rekayasa Konstruksi (JOS-MRK) 2(3): 298-303. https://doi.org/10.55404/jos-mrk.2021.02.03.298-303

SAVE International. (2020). VM Guide: A Guide to the Value Methodology Body of Knowledge. SAVE International.

Silvianengsih, S., Misriani, M., Natalia, M., Ihdini, G. & Fadila, J. (2023). Analisa Perbandingan Biaya dan Waktu Pelaksanaan Dinding Penahan Tanah Secant Pile dengan Diaphragm Wall pada Proyek Revitalisasi Taman Ismail Marzuki. Fropil 11(2): 102-111.

Sugiyono. (2023). Metode Penelitian Kuantitatif dan Kualitatif R&D. Bandung: Alfabeta.

Uddin, M.A. & Rahman, M. (2024). A Case Study of The Performance of A Pile-Supported Bracing Method for Basement Building. International Journal of Engineering & Applied Sciences (IJEAS) 16(1): 1-15. https://doi.org/10.24107/ijeas.1343322

Downloads

Published

2026-11-10

How to Cite

Andi Isra Dwi Rahayu AS, Kartono Wibowo, & Abdul Rochim. (2026). Value Engineering For Deep Excavation Retaining Systems With A Balanced Budget Approach. International Journal of Health Engineering and Technology, 5(4). https://doi.org/10.55227/ijhet.v5i4.1283