Analysis of Construction Time Acceleration Using the Crashing Method in the North Maluku Language Office Building Construction Project
DOI:
https://doi.org/10.55227/ijhet.v4i4.447Keywords:
Construction Management, Critical Path Method, Project Acceleration, Project Scheduling, Time-Cost Trade-OffAbstract
This study addresses accelerating construction time for the North Maluku Language Office Building using the crashing method. The project aims to provide adequate infrastructure to support linguistic and administrative functions, scheduled over 135 calendar days starting August 2024. Employing a descriptive quantitative design, the research involved direct field observations and Microsoft Project software to analyze critical path activities eligible for crashing. The population focused on all critical path tasks, with purposive sampling targeting those amenable to overtime acceleration. Data analysis included cost variance and percentage calculations for time reduction. Results show that applying overtime reduced the project duration from 67 days to as few as 44.67 days, with labor costs increasing between 6.7% and 26.82% depending on overtime hours. Cost and scheduling analyses facilitated selecting the most cost-effective acceleration scenario. The study concludes that the crashing method effectively balances time reduction and cost increments, serving as a practical strategy for managing delays in regional public sector projects. These findings provide critical insight for optimizing schedule compression while maintaining quality.
Downloads
References
Anggara, E. R., & Idi, N. (2021). Analisis Percepatan Waktu Menggunakan Metode Crashing pada Pembangunan Tower 7 Proyek Apartement Tokyo Riverside. Seminar Nasional Ketekniksipilan, Infrastruktur dan Industri Jasa Konstruksi (KIIJK), 1.
Dwiantoro, D., Yoansa, A. Y., Indrayana, D. V., Mentari, S., & Widyatami, F. S. (2024). Analisis Faktor Penyebab Keterlambatan Proyek ‘XYZ.’ Jurnal Talenta Sipil, 7(1), 388. https://doi.org/10.33087/talentasipil.v7i1.490
Kemendikdasmen. (2025, May 31). Kemendikbudristek Resmikan Gedung Kantor Bahasa Provinsi Maluku. Kementrian Pendidikan Dasar dan Menengah. Retrieved from https://staging-portal.kemdikbud.go.id/berita/4616-Kemendikbudristek-Resmikan-Gedung-Kantor-Bahasa-Provinsi-Maluku
Mahapatni, I. A. P. S. (2019). Metode Perencanaan dan Pengendalian Proyek Konstruksi. UNHI Press.
Sugiyono. (2021). [Reference details pending].
Sugiyono. (2022). [Reference details pending].
Sudaryono. (2023). [Reference details pending].
Atlan. (2024). [Reference details pending].
Emzir. (2023). [Reference details pending].
Creswell, J. W. (2018). [Reference details pending].
Sutciana, L. A., Maranatha, W., Mt, M., & Naingollan, I. (2020). Penerapan Metode Fast Track Untuk Percepatan Penjadwalan (Studi Kasus: Pembangunan Gedung Laboratorium Vokasi dan Industri Kreatif Vokasi Tahap 1 Universitas Brawijaya). Institut Teknologi Nasional
Mayaut, P. F. (2025, May 31). Kantor Bahasa Maluku bangun kantor untuk pusat konsultasi bahasa. Antara Maluku. Retrieved from https://ambon.antaranews.com/berita/159099/kantor-bahasa-maluku-bangun-kantor-untuk-pusat-konsultasi-bahasa
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2025 Landi Nasarudin, Inge Anggitasari, Olvi Pamadya Utaya Kusuma, Susilowati

This work is licensed under a Creative Commons Attribution-NonCommercial 4.0 International License.